About The Project
The scope of this environmental construction project included the aeration and remediation of two (2) Soil Treatment Facilities, containing approximately 120,000 tons of Hydrocarbon contaminated soils. In addition to the soil bio-remediation, Enviro-Ex completed the safe removal and replacement of two (2) large 8-mil tarp covers.
SECTOR: | Environmental, |
VALUE: | $ 250,000.00 |
COMPLETION: | September 2018 |
Key Features: |
|
Responsibilities
- Prime Contractor
- UAV Drone Survey
- Treatment of two (2) Soil Treatment facilities
- AEC Excavations
- Review and implement soil treatment technologies
- Mines Act regulations